The current natural gas price in West Texas (the WaHa hub, north of Coyanosa, TX) is negative. And has been for a while. The price peaked (dipped?) to -$9/MCF a couple months ago. That means gas producers had to pay $9 per MCF for it to be taken away. Oil in the Permian comes with gas, a lot of it, so to produce oil, you need to get rid of gas. Wells I'm familiar with have 4000-5000 cubic feet of gas per barrel of oil. Recall in oilfield M = thousand, so that's 4-5 MCF per bbl of oil.
There is no free gas pipeline capacity to get gas out of West Texas. Any time new pipelines are built, they are filled within months.
This makes a ton of sense for oil producers (which are also gas producers) who can sell their gas for less of a loss (potentially a profit!) and also for MSFT who can lock in long term contracts for minimal cost. I'd guess these contracts are for $1-2/MCF which is win/win for the oil companies in the area and MSFT.
epistasis 1 hours ago [-]
This might make sense for oil producers to get rid of their natural gas, which is nearly a waste material, but I'm struggling to understand how it makes sense for Microsoft. Despite the cheap natural gas, and an abundance of investors and builders with natural gas expertise, in the competitive electricity generation market everybody is deploying solar and batteries in west Texas because it's still more profitable than gas generation.
Further, there's a gas turbine shortage so Microsoft choosing to put their (presumably limited) allocation of gas turbines in West Texas, where they have good alternatives, seems a bit mysterious. Why not save that massive amount of turbines for the northeast DCs, where renewables work far poorer yet gas is more reliable?
The reasons that seem most convincing to me:
1. Political environment is hostile to renewables and Microsoft doesn't want to paint a target on their back by choosing solar plus batteries, the choice others are making in West Texas.
2. Grid connection drastically changes economics, but pipelines for gas are cheap or something, so the massive cost and delay from grid interconnection simply isn't worth it
3. There are particular political favors going on with Chevron, e.g. Chevron wants gas in the area and is willing to increase MS's turbine allocation if they do it in west Texas, or Chevron is helping get around pesky local political approvals for data centers, or something like that.
The cost of gas does not seem like a justification for this, though.
stonogo 1 hours ago [-]
The cost of gas is completely irrelevant. In order to bring a new large load onto the grid, you have to coordinate with ERCOT, and they just made that process more tedious. Once you get your grid connection approved and built out, you have to source your own power anyway, and frankly there just isn't enough power on the market to realize the stated datacenter buildout goals in this country.
In short, you're going to have to build your own power plant anyway, so why bother with the grid? Gas is the cheapest, fastest zero-to-production choice for onsite power generation, and has been for a long time. Unless you're dealing with nuclear, the fuel cost just doesn't matter compared to the rest of the buildout, and gas wins because you can take off-the-shelf turbines and bolt them down.
You can only get away with it in places that don't care about environmental regulations, which are the places most likely to approve new buildout of gas infrastructure anyway. Nobody in the northeast is going to approve the creation of a brand new carcinogen factory.
epistasis 1 hours ago [-]
> Gas is the cheapest, fastest zero-to-production choice for onsite power generation, and has been for a long time.
Is it, though? There's a ton of projects out there waiting to get their solar on the grid in west Texas, partnering with one of them and launching the project early while waiting on the interconnection queue, and adding enough batteries, gives a more robust solution right now without the SPOF nature of large single generators.
Add to that the long backorder list for gas turbines right now, with no end in sight, and I'm surprised that Microsoft would power this particular location with turbines because it's probably their best chance to do off-grid massive solar projects.
Massive off-grid solar is what China is choosing for some absolutely massive new industrial projects. Nuclear is a no-go because it takes so long to deploy, but solar + batteries are cheap COTS and available in abundance, unlike gas turbines.
chasd00 25 minutes ago [-]
> Is it, though? There's a ton of projects out there waiting to get their solar on the grid in west Texas,
gas turbines run at night too so there's no storage/backup supply issue to consider. They also take up significantly less space than wind or solar and those data centers are already gigantic.
stonogo 58 minutes ago [-]
> Is it, though?
Yes.
There is no point in waiting for interconnection when you can just... not do that, and do all your generation behind the meter, with complete control of the generation to match your load. Solar wants an interconnect so they can sell off surplus; with gas you just turn the dial down to meet the load and walk away.
The clock is running on the datacenter goldrush. 70-90% of the capex window is going to be soaked up just with construction time. Introducing a capricious ERCOT permit process and shopping around for friendly solar projects to hop in bed with makes no sense when you can just write a check and solve the problem forever.
I'd bet the deal with Chevron was to enable Microsoft to hop the queue here and get those GEV turbines soonest.
epistasis 54 minutes ago [-]
I'm not saying wait for an interconnection, I'm saying take a project that already has a fully developed plan, that's waiting for interconnection, and build the DC right there next to it, beef up the battery component of the plan and go to town. Interconnection happens some time in the future, giving far more financial opportunities for everyone, but in the interim the electricity goes fully to the DC.
rayiner 2 minutes ago [-]
[delayed]
alex43578 34 minutes ago [-]
Because I expect the economics of enough batteries to carry a data center’s worth of demand through the night and morning is too expensive compared to essentially free natural gas.
Data centers would ideally run at ~100% utilization, so any drop in solar output needs to be fully met by batteries.
jeffbee 25 minutes ago [-]
> Data centers would ideally run at ~100% utilization
I don't think this is broadly accepted among major data center operators.
declan_roberts 2 hours ago [-]
Even corporate ESG policies bend the knee to cheap Texas energy!
caminante 1 hours ago [-]
Profits still ain't easy.
Cheap gas is great, but 2.67GW of new build natural gas in this market will cost $6-8 billion in fixed costs. You need wholesale pricing of ~$50-60/MWh ... OVER 25 years! ... to recover just the fixed costs.
For West Texas, prices averaged mid-$30s over the last year.
Microsoft has all of the leverage here, and Chevron wants a big announcement in an area where they don't have a lot of experience.
advisedwang 2 hours ago [-]
Microsoft says [1] they're going to be carbon negative by 2030. Hard to see them doing that while deploying gigawatts of new fossil fuels.
Its easy, they are going to use fancy accounting to make it come true. Produce a ton of carbon, then buy a cheap, under-priced carbon credit to make it be a zero.
ray_v 1 hours ago [-]
it's easy ... they'll just change the definition of "carbon negative"!
epistasis 3 hours ago [-]
Fascinating they're going this direction when solar and batteries are so cheap in Texas...
Nearly all new additions to the grid are solar, wind, and storage right now on Texas' grid. Not because of Texas regulations, but because Texas' grid is one of the few grids where generation decisions are all made by independent investors trying to make money.
Especially with the shortage in gas turbine manufacturing, very surprising! Not sure if this says more about Microsoft or datacenters.
bob1029 2 hours ago [-]
West Texas is like Costco for natural gas.
There are cases where the fields can produce more than the pipelines can carry away. If you put your gigantic gas turbines right next to the fields you can obtain access to some extremely cheap fuel. They might even pay you to burn it sometimes. Negative gas prices are a thing.
epistasis 2 hours ago [-]
And despite that, when there's any sort of price pressure, like there is for new electricity grid additions from investors, solar and batteries completely dominate the choice over natural gas in Texas.
Look at the map for 2026 of the grid buildout in Texas at the bottom of this page:
All solar and batteries (yellow and black), with a few tiny blue dots for gas. It was the same story in 2025. And it will be the same story in 2027 because solar and batteries are getting even cheaper.
These are all decisions from private investors, trying to make money, and choosing solar and batteries over gas in the market where gas is the cheapest in the world, gas is like a waste product that's hard to get rid of.
Why would Microsoft choose dirty energy when all the profit-driven investors are choosing cheaper solar and storage?
ElevenLathe 2 hours ago [-]
This is just a guess, but is the reason the same one that the gas is cheap all the way out in BFE west Texas? In other words, even if you could generate electricity from wellhead gas more cheaply than a bunch of wind turbines, solar panels, and batteries just west of Fort Worth, can you actually export it to east Texas where all the demand is? The solution here being: let's build our giant demand machine directly on the steppe and skip all that expensive infra, because data is much cheaper to move than energy.
bob1029 2 hours ago [-]
> data is much cheaper to move than energy
It's something like 5-10 orders of magnitude cheaper to move information over fiber than it is to move the energy required to produce that same information through a [pipe/power]line.
gnerd00 2 hours ago [-]
West Texas is also a basket of methane leakage -- see CarbonMapper et al
credit_guy 59 minutes ago [-]
But they are using wind:
> A majority of the generation will come from large GE Vernova (NYSE: GEV) turbines.
alex43578 31 minutes ago [-]
Unless the article specifies wind, GE Vernova makes gas turbines too.
dtagames 2 hours ago [-]
Mostly it says that the oil business runs the show here in Texas, and in Washington.
epistasis 2 hours ago [-]
But I'm curious how oil could run the show for Microsoft though. Even if Microsoft wanted gas backup, they could add solar to the build, shut off the turbines during the day, and save money over an all gas setup.
Perhaps Microsoft had better ability to overturn local opposition to data centers if they had Chevron's political influence over the politicians too?
dtagames 2 hours ago [-]
What I meant was that all political and economic decisions here go in favor of oil. The war, the proposed laws to make Chinese EVs illegal, the softening of environmental regulations, etc.
Chevron and the US Government are joined at the hip, so these kind of deals "flow" naturally.
rconti 1 hours ago [-]
DC?
softwaredoug 2 hours ago [-]
While the US stays oil rich, we should expect the US to be a laggard in ending use of fossil fuels. China and EU are not oil rich, they’ll make a faster transition.
Of course it’s idiotic to actively hobble clean energy. Or to put your finger on the scale for one source of energy, like the current administration does.
But it’s not crazy to argue for “energy abundance” where the market just picks the cheapest energy on the market in the US and that just gradually moves cleaner over time.
epistasis 2 hours ago [-]
Well what I'm saying that is that on the Texas grid, solar and storage and wind are the cheapest energy, and being deployed in massive amounts because only on the Texas can an investor make money by providing the cheapest energy. (For most utilities, they take a fixed rate of profit and are incentivized to use the most expensive possible energy if they can get away with it.)
So Texas is not a laggard when it comes to clean energy, they are actually driving clean energy forward the most, because clean energy is the cheapest and most profitable energy. And that's despite Texas having natural gas that's insanely cheap right from Henry Hub.
What this tells me is that like most hyperscalers, Microsoft is not price sensitive on the electricity side, because energy costs are tiny compared to the massive capital costs of the GPUs. But why would they go this direction? What political influence would make Microsoft choose more expensive electricity, when in the past they've been fairly good at driving clean energy forward in their data center power choices, and they'd pay a premium on energy costs to go with clean energy?
chasd00 16 minutes ago [-]
> But why would they go this direction?
sibling comment has it, they want to do power generation on site and not connected to the grid and all the PITA that come with that. Further, they can pitch power independence to the locals which removes a big argument from the anti-datacenter crowd. Finally, the power gen i saw at Stargate in Abilene TX which was maybe 10 units (if that's what they're called) took up maybe 30 acres of land so they're not very big compared to the rest of the campus.
tech_ken 2 hours ago [-]
I can think of a few angles that might have pushed them towards gas, mainly (a) they wanted on-demand generation cap, (b) they didn't want to get into the batteries game at the volume they'd require, or (c) they didn't want to deal with securing the space needed to produce 2.6GW of solar. Also yeah they're definitely not price-sensitive, any of the hyperscalars is more than happy to pay extra to get exactly what they want.
edit: for example that EIA list of new solar projects you linked indicates that the largest battery installations going up in '26 are all ~500MW, and that there are only four of them (of that size). I think the energy intensity of a multi-GW datacenter is the main reason that they're not going for solar here.
teepo 9 minutes ago [-]
[flagged]
jmward01 36 minutes ago [-]
I love how they are using a company named 'Solar Turbines'. Such an obviously misleading name. (From their website)[1]:
Powering the future through innovative, sustainable energy solutions.
Solar Turbines Incorporated, headquartered in San Diego, California, is a wholly owned subsidiary of Caterpillar Inc. Solar manufactures the world’s most widely used family of mid-sized industrial gas turbines, ranging from 1 to 39 megawatts. More than 17,000 Solar units are installed in more than 100 countries with more than 3 billion operating hours. Solar is a leading provider of energy solutions, featuring an extensive line of gas turbine-powered compressor sets, mechanical drive packages, and generator sets.
To be fair, solar turbines has had the name since 1929 (they were then called solar aircraft company). It’s not like they’re being intentionally misleading.
jmward01 21 minutes ago [-]
Thanks for point that out. I missed that context.
mixdup 2 hours ago [-]
I guess that whole carbon negative by 2030 goal got shuffled down the priority list
tencentshill 20 minutes ago [-]
Another illustration that corporations do not have morals or ideologies. Do not anthropomorphize the lawnmower.
bob1029 3 hours ago [-]
> A majority of the generation will come from large GE Vernova (NYSE: GEV) turbines and associated electrical infrastructure, with additional capacity provided by Solar Turbines, a wholly owned subsidiary of Caterpillar Inc. (NYSE: CAT).
When they say "large GE Verona", they mean the 7HA. This is an actual power plant with proper emissions controls. Not the aeroderivatives in parking lots we've seen so far.
> Their plan includes the use of seven U.S.-made GE Vernova Inc. GEV 7HA natural gas turbines to deliver the plant's initial capacity.
this showed up in a google image search of all things, take a look at page 14. Looks like that is the plan, even laying down nat. gas pipelines to the data centers. The bullet points on the map don't have city names but if you compare to that graphic to a regular map of Texas they dots align to some of the proposed datacenter sites.
I had to go read the article to check because other operators have been entering into PPAs with oil companies, but for photovoltaic power. E.g. Google and TotalEnergies.
California's progressive policies have pushed out both data centers and Chevron out of the area. I'm sitting here wondering why Newsom is so proud of his achievements.
ZebulonP 1 hours ago [-]
Yeah, why would a governor be proud of pushing out two things that are unpopular with his constituents...
gnerd00 1 hours ago [-]
Newsom aside, the idea is to change from oil to non-oil, efficient from mono-industrial.. The US Oil minions claim to be blind to this and cite quarterly profits, again
theredleft 1 hours ago [-]
lol no way it lasts that long
flixspiek 2 hours ago [-]
[flagged]
whalesalad 3 hours ago [-]
> A majority of the generation will come from large GE Vernova turbines and associated electrical infrastructure, with additional capacity provided by Solar Turbines, a wholly owned subsidiary of Caterpillar Inc.
Solar turbines is an interesting name for a gas turbine company. "It's green energy, we put solar in our name"
infecto 3 hours ago [-]
Quick search shows the reason is nothing to do with your sarcasm.
Its origin is traced back to a 1929 company, Solar Aircraft Company.
I agree with OP that the name, while maybe not deliberately, is really confusing in 2026. I thought that was a wind turbines or a solar panel technology, definitely not gas.
infecto 3 hours ago [-]
And it takes all of 30seconds to look up instead of posting sarcastic hyperbole that the company is trying to greenwash their product by name when it’s a 100 year old company name.
Confusing as it may be for people like yourself, I don’t think it really defends posting sarcasm that is not based in reality.
anon7725 54 minutes ago [-]
It's 2026 - they should change their fucking name.
whalesalad 2 hours ago [-]
I didn't really think it was greenwashing, just hilarious to have one of the largest gas turbine companies in the world named "solar turbines"
infecto 2 hours ago [-]
> "It's green energy, we put solar in our name"
You can call this whatever you want.
skupig 1 hours ago [-]
We call them "jokes"
thelastgallon 3 hours ago [-]
Solar Turbines is one of the world's leading manufacturers of industrial gas turbines, with more than 17,000 installed in 100 countries
tokai 3 hours ago [-]
Much like that scoundrel Aurelian reviving the cult of Sol Invictus to greenwash the late roman empire. /s
21asdffdsa12 2 hours ago [-]
Sorry, but who in his right mind, signs contracts for 20 years - could you have imagined the world today 20 years ago? No and no. All one should do is sign snippet contracts of 5 years with the offer of an option to predefined condition. Split it into 4 sequences with a renewal.
doikor 1 hours ago [-]
Very normal. Here in Europe (well nordics at least) pretty much all the capacity of any wind farm is already sold before construction begins. The PPA (power purchasing agreement) is usually pretty much required to get the loan/funding anyway.
Basically most projects start with the wind company using its own money to find a site and get it approved and then they go and try to find someone to sell the electricity to at a fixed rate before construction begins as selling directly to the spot market has way too much risk for the banks to give loans.
Not sure how different it is in Central Europe with solar as there isn’t much solar up here in the north (just doesn’t make much sense as during the 3 to 4 months in the winter when electricity price is at the yearly maximum you produce effectively nothing)
bluGill 52 minutes ago [-]
Many people. My house loan was 30 years. Commercial real estate is often 20. Commercial 30 year bonds are common.
Many investments won't pay off unless there is a 30 year plan so lots of investors work on that long term. Even if an investment pays off sooner you often are accounting better off longer terms - see an accountant
Rendered at 17:49:26 GMT+0000 (Coordinated Universal Time) with Vercel.
There is no free gas pipeline capacity to get gas out of West Texas. Any time new pipelines are built, they are filled within months.
This makes a ton of sense for oil producers (which are also gas producers) who can sell their gas for less of a loss (potentially a profit!) and also for MSFT who can lock in long term contracts for minimal cost. I'd guess these contracts are for $1-2/MCF which is win/win for the oil companies in the area and MSFT.
Further, there's a gas turbine shortage so Microsoft choosing to put their (presumably limited) allocation of gas turbines in West Texas, where they have good alternatives, seems a bit mysterious. Why not save that massive amount of turbines for the northeast DCs, where renewables work far poorer yet gas is more reliable?
The reasons that seem most convincing to me:
1. Political environment is hostile to renewables and Microsoft doesn't want to paint a target on their back by choosing solar plus batteries, the choice others are making in West Texas.
2. Grid connection drastically changes economics, but pipelines for gas are cheap or something, so the massive cost and delay from grid interconnection simply isn't worth it
3. There are particular political favors going on with Chevron, e.g. Chevron wants gas in the area and is willing to increase MS's turbine allocation if they do it in west Texas, or Chevron is helping get around pesky local political approvals for data centers, or something like that.
The cost of gas does not seem like a justification for this, though.
In short, you're going to have to build your own power plant anyway, so why bother with the grid? Gas is the cheapest, fastest zero-to-production choice for onsite power generation, and has been for a long time. Unless you're dealing with nuclear, the fuel cost just doesn't matter compared to the rest of the buildout, and gas wins because you can take off-the-shelf turbines and bolt them down.
You can only get away with it in places that don't care about environmental regulations, which are the places most likely to approve new buildout of gas infrastructure anyway. Nobody in the northeast is going to approve the creation of a brand new carcinogen factory.
Is it, though? There's a ton of projects out there waiting to get their solar on the grid in west Texas, partnering with one of them and launching the project early while waiting on the interconnection queue, and adding enough batteries, gives a more robust solution right now without the SPOF nature of large single generators.
Add to that the long backorder list for gas turbines right now, with no end in sight, and I'm surprised that Microsoft would power this particular location with turbines because it's probably their best chance to do off-grid massive solar projects.
Massive off-grid solar is what China is choosing for some absolutely massive new industrial projects. Nuclear is a no-go because it takes so long to deploy, but solar + batteries are cheap COTS and available in abundance, unlike gas turbines.
gas turbines run at night too so there's no storage/backup supply issue to consider. They also take up significantly less space than wind or solar and those data centers are already gigantic.
Yes.
There is no point in waiting for interconnection when you can just... not do that, and do all your generation behind the meter, with complete control of the generation to match your load. Solar wants an interconnect so they can sell off surplus; with gas you just turn the dial down to meet the load and walk away.
The clock is running on the datacenter goldrush. 70-90% of the capex window is going to be soaked up just with construction time. Introducing a capricious ERCOT permit process and shopping around for friendly solar projects to hop in bed with makes no sense when you can just write a check and solve the problem forever.
I'd bet the deal with Chevron was to enable Microsoft to hop the queue here and get those GEV turbines soonest.
Data centers would ideally run at ~100% utilization, so any drop in solar output needs to be fully met by batteries.
I don't think this is broadly accepted among major data center operators.
Cheap gas is great, but 2.67GW of new build natural gas in this market will cost $6-8 billion in fixed costs. You need wholesale pricing of ~$50-60/MWh ... OVER 25 years! ... to recover just the fixed costs.
For West Texas, prices averaged mid-$30s over the last year.
Microsoft has all of the leverage here, and Chevron wants a big announcement in an area where they don't have a lot of experience.
[1] https://www.microsoft.com/en-us/corporate-responsibility/sus...
Nearly all new additions to the grid are solar, wind, and storage right now on Texas' grid. Not because of Texas regulations, but because Texas' grid is one of the few grids where generation decisions are all made by independent investors trying to make money.
Especially with the shortage in gas turbine manufacturing, very surprising! Not sure if this says more about Microsoft or datacenters.
There are cases where the fields can produce more than the pipelines can carry away. If you put your gigantic gas turbines right next to the fields you can obtain access to some extremely cheap fuel. They might even pay you to burn it sometimes. Negative gas prices are a thing.
Look at the map for 2026 of the grid buildout in Texas at the bottom of this page:
https://www.eia.gov/todayinenergy/detail.php?id=67205
All solar and batteries (yellow and black), with a few tiny blue dots for gas. It was the same story in 2025. And it will be the same story in 2027 because solar and batteries are getting even cheaper.
These are all decisions from private investors, trying to make money, and choosing solar and batteries over gas in the market where gas is the cheapest in the world, gas is like a waste product that's hard to get rid of.
Why would Microsoft choose dirty energy when all the profit-driven investors are choosing cheaper solar and storage?
It's something like 5-10 orders of magnitude cheaper to move information over fiber than it is to move the energy required to produce that same information through a [pipe/power]line.
> A majority of the generation will come from large GE Vernova (NYSE: GEV) turbines.
Perhaps Microsoft had better ability to overturn local opposition to data centers if they had Chevron's political influence over the politicians too?
Chevron and the US Government are joined at the hip, so these kind of deals "flow" naturally.
Of course it’s idiotic to actively hobble clean energy. Or to put your finger on the scale for one source of energy, like the current administration does.
But it’s not crazy to argue for “energy abundance” where the market just picks the cheapest energy on the market in the US and that just gradually moves cleaner over time.
So Texas is not a laggard when it comes to clean energy, they are actually driving clean energy forward the most, because clean energy is the cheapest and most profitable energy. And that's despite Texas having natural gas that's insanely cheap right from Henry Hub.
What this tells me is that like most hyperscalers, Microsoft is not price sensitive on the electricity side, because energy costs are tiny compared to the massive capital costs of the GPUs. But why would they go this direction? What political influence would make Microsoft choose more expensive electricity, when in the past they've been fairly good at driving clean energy forward in their data center power choices, and they'd pay a premium on energy costs to go with clean energy?
sibling comment has it, they want to do power generation on site and not connected to the grid and all the PITA that come with that. Further, they can pitch power independence to the locals which removes a big argument from the anti-datacenter crowd. Finally, the power gen i saw at Stargate in Abilene TX which was maybe 10 units (if that's what they're called) took up maybe 30 acres of land so they're not very big compared to the rest of the campus.
edit: for example that EIA list of new solar projects you linked indicates that the largest battery installations going up in '26 are all ~500MW, and that there are only four of them (of that size). I think the energy intensity of a multi-GW datacenter is the main reason that they're not going for solar here.
Powering the future through innovative, sustainable energy solutions.
Solar Turbines Incorporated, headquartered in San Diego, California, is a wholly owned subsidiary of Caterpillar Inc. Solar manufactures the world’s most widely used family of mid-sized industrial gas turbines, ranging from 1 to 39 megawatts. More than 17,000 Solar units are installed in more than 100 countries with more than 3 billion operating hours. Solar is a leading provider of energy solutions, featuring an extensive line of gas turbine-powered compressor sets, mechanical drive packages, and generator sets.
[1] https://www.solarturbines.com/en_US/about-us.html
When they say "large GE Verona", they mean the 7HA. This is an actual power plant with proper emissions controls. Not the aeroderivatives in parking lots we've seen so far.
> Their plan includes the use of seven U.S.-made GE Vernova Inc. GEV 7HA natural gas turbines to deliver the plant's initial capacity.
https://finance.yahoo.com/sectors/energy/articles/chevron-mi...
Why not use all that wasted heat energy to power all these datacenters?
(and why not build the datacenters at the Bakken formation)
You can see the burnoff from SPACE and it's for months at a time at each location, tell me that does nothing to global temperatures?
(look at the date on these photos, two decades of burnoff wasted energy)
* https://www.cnbc.com/2013/01/28/shale-gas-boom-now-visible-f...
* https://www.smithsonianmag.com/smart-news/at-night-giant-fie...
https://www.esig.energy/wp-content/uploads/2025/05/ESIG_LLTF...
https://pv-magazine-usa.com/2026/02/09/totalenergies-signs-1...
Also Google and itself. I guess there's a difference between Google and Microsoft after all.
https://storage.googleapis.com/gweb-uniblog-publish-prod/doc...
Solar turbines is an interesting name for a gas turbine company. "It's green energy, we put solar in our name"
Its origin is traced back to a 1929 company, Solar Aircraft Company.
https://en.wikipedia.org/wiki/Solar_Turbines
Confusing as it may be for people like yourself, I don’t think it really defends posting sarcasm that is not based in reality.
You can call this whatever you want.
Basically most projects start with the wind company using its own money to find a site and get it approved and then they go and try to find someone to sell the electricity to at a fixed rate before construction begins as selling directly to the spot market has way too much risk for the banks to give loans.
Not sure how different it is in Central Europe with solar as there isn’t much solar up here in the north (just doesn’t make much sense as during the 3 to 4 months in the winter when electricity price is at the yearly maximum you produce effectively nothing)
Many investments won't pay off unless there is a 30 year plan so lots of investors work on that long term. Even if an investment pays off sooner you often are accounting better off longer terms - see an accountant